District hears engineering updates: Roxanna line ~74.6% complete, Millstone corrective work, tank-site talks continue

Jan 17, 2026

Bell Engineering updated the board on Roxanna Waterline progress, CSX inspection delays for a railroad bore, Millstone sewer corrective actions and multiple design advances; the board approved Bell and GRW pay requests, monthly bills, and surplus of three vehicles, then adjourned.

The full story

At the Jan. 15 regular meeting, the Electric County Water and Sewer District received detailed engineering updates from Bell Engineering and GRW and approved several administrative pay requests and routine items.