Commissioners were told a dredge breakdown delayed the beach project; mobilization is expected in February, sand pumping around March 1 with approximately a 60-day sand phase, followed by breakwater construction moving north.

The full story

A commissioner updated the Gulf County Board of County Commissioners on the beach-dredging project, saying a dredge breakdown has delayed work and that contractors now expect to mobilize in February and begin sand pumping around March 1.