The commission recommended approval of an amendment to the Orchards development agreement to add pavement width allowing two eastbound lanes and asked that parcel 3835 South be completed in phase 1; commissioners noted traffic constraints where private property (KOA) limits widening and recorded some reservations about overall benefit.

The Perry City Planning Commission on the record recommended approval of an amendment to the Orchards development agreement, a measure staff said responds to a UDOT-required closure and related traffic impacts. Staff member Bob Barnhart told the commission the developer and the city engineer added "2 to 3 feet of asphalt on the north side" to allow two eastbound lanes with a separate right‑turn lane, through lane and left‑turn lane to reduce pressure on the 3600 South intersection.

Barnhart said UDOT conducted its own internal analysis and did not require additional traffic studies; commissioners pressed staff on how far the widening would extend. Barnhart replied the proposed widening "doesn't widen all the way down" to 1200 West because private property, including a KOA campground, constrains right‑of‑way. He said the developer is paying for the widening and that the added pavement "gave enough width for all 3 of those lanes across."

Following discussion about phasing and remaining constraints, a commissioner moved to "approve ordinance 25‑u amendment to [the] development agreement" and to include parcel 3835 South — shown in the plans as part of phase 2 — to be completed as part of phase 1. The motion was seconded and carried; recorded roll‑call responses show Commissioner Broadhead, Commissioner Moss and Commissioner Thompson voting yes (Thompson added he "will say yes with the stipulation that I still don't love it"). The commission will forward its recommendation and recorded comments to city council.

The record contains inconsistent references to the project name (staff and earlier materials called it "Olsen Orchards," while the motion language used "Bolton Orchards"). Staff provided the plan set and maps during the hearing; the commission did not change the underlying engineering requirement that final grading, stormwater and detailed utilities be resolved in the engineering application.

Next steps: The commission's recommendation will go to city council for final action; staff said council could accept the recommendation, add conditions, or deny the amendment.