Board approves $6,500 change order to add performance bond for fairgrounds ADA parking project

Jan 27, 2026

County staff reported a change order with Planet Excavation adding a $6,500 performance bond to the Fairgrounds ADA parking contract, raising the contract from $199,856.46 to $206,356.46; commissioners agreed to add performance bonds to future bids.

The full story

At the workshop, staff reported a change order to the Planet Excavation contract for the Fairgrounds ADA parking project. Justin explained the contractor agreed to add a performance bond at a cost of $6,500, which increases the contract total from $199,856.46 to $206,356.46.