Sheriff’s facilities face multiyear capital needs: EOC, security upgrades and proposed crime-lab design
Summary
Facilities staff described rising utilities tied to a new 100%-electric EOC, a $168,000 security-system replacement, parking-light upgrades and a multi-million-dollar crime-lab build that may require design funding now but major construction later.
Get email alerts on the Facilities And Capital topic
No spam. Unsubscribe anytime.
Mitch, the county facilities representative, told the Budget Committee the sheriff’s buildings-and-grounds portfolio has been unusually active this year, with several projects coming online and two major facilities—an Emergency Operations Center (EOC) and a sewer lift station—scheduled to be completed around mid-December.
"The EOC is 100% electric," Mitch said, explaining that increased electricity needs account for a roughly $59,000 rise in utilities in the sheriff’s facilities budget. He listed near-term capital priorities: a security-system replacement (servers, touchscreens, PCs) estimated at about $168,000; replacement of a 1998 chiller; parking-lot lighting upgrades to LED for reliability and life-safety reasons; and ongoing camera and Metasys control upgrades.
Mitch also discussed a longstanding crime-lab expansion request. He said a full design proposal for an upstairs crime lab has been on the five-year plan for several years and argued the county needs to move forward rather than rely exclusively on the state crime lab for backlogged work. A committee exchange discussed costs: Mitch cited a recent bid that put build-out near $3,000,000; a commissioner noted that a $1,000,000 design fee would be a poor use if the county were unwilling to fund the larger build price, estimating total project cost could be $4–5 million depending on scope. Mitch said the design work would likely carry into 2027 and that some capital requests had previously been split across budgets, which he consolidated into buildings-and-grounds west for this cycle.
Mitch emphasized life-safety and maintenance issues—failing lighting, aging chillers and end-of-life security hardware—and said some items are mandated by inspection standards. He asked the committee to consider funding the identified capital improvements and said a feasibility study covering multiple facilities should wrap up this year.
Next steps: the committee asked staff to refine cost estimates, consider funding sources (general fund vs. buildings-and-grounds fund) and return with options that align design work to a realistic construction funding plan.