Board hears revised elementary performance‑space plan; trustees split over further architect engagement

Ann Arbor Public Schools Board of Education · January 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District capital staff presented a compromise design for elementary gathering spaces—fixed raised platforms with optional adaptable extensions—while acknowledging limitations for full grade‑level choral rigs and parent capacity. Trustees pressed for further meetings; a motion to require a Thurston‑style Q&A with music teachers and designers failed on a roll‑call vote.

Capital program staff and the district’s owner’s representative presented a revised approach to performance spaces in new K‑5 buildings at the July 30 meeting, outlining design tradeoffs and options for accommodating instruction, lunch, and performances.

The team described three primary gathering modes in the new buildings—cafe, gym and the “heart” (a mid‑building gathering space)—and showed plans for a fixed raised platform (roughly the 16×24 size of the board’s dais) that can be augmented with adaptable platform modules to expand depth or front projection area when needed. The presentation emphasized that larger platform footprints reduce audience seating and can impinge on required egress; the design assumes some events that require a wider stage could be hosted at upgraded middle‑school auditoriums.

Owner’s representative Kevin Stansbury said the proposed solution balances everyday lunch/gathering needs and occasional full‑school presentations: “This allows for a full school presentation where no students are on the stage,” he said while demonstrating how adaptable platforms could expand the usable performance area.

Trustees and teachers asked detailed questions about riser width for choral performances, whether curtains could be mounted at the front of the platform, accessibility and curtain storage, and scheduling impacts when gyms are used for both PE and assemblies. Performing‑arts teachers urged additional design work and a seat‑by‑seat consideration of choral riser widths; the district offered to continue stakeholder engagement and to study middle‑school auditorium upgrades that could host large parent audiences or full‑grade performances.

Trustee Mohammed moved for a Thurston‑style Q&A with music‑teacher leadership and advisory groups at a bond‑committee meeting and for the board to act afterward; that motion (moved by Mohammed, seconded by Wilkins) failed on roll call. Several trustees said they appreciated staff engagement and were concerned about delaying projects by reopening major design elements, while others argued additional targeted meetings with architects would be appropriate given teacher input.

What’s next: Capital staff will continue stakeholder engagement, provide additional details on adaptable platform options and middle‑school auditorium improvement plans, and return to the board with prioritized recommendations.