County engineer: Libertyville Road, Grama Tree bridge projects moving; federal grant shows progress

Jan 30, 2026

The county engineer told supervisors that bids for Libertyville Road and the Grama Tree bridge are closing and a successful bidder is expected soon; the engineer said the bridge project includes federal funding and extra site work to meet federal slope requirements.

The full story

The Jefferson County engineer updated the Board of Supervisors on Jan. 19 that bids for Libertyville Road and the Grama Tree bridge project are moving forward and a successful bidder should be known within about a week. He estimated the Libertyville Road job could take roughly 60–90 working days once construction begins.