Council Authorizes Staff to Finalize West Interceptor Segment 2 Contract
Nov 5, 2025
Nov 5, 2025
Council accepted the low bid from Guijo Construction ($3,315,089.38) for West Interceptor Segment 2 and authorized staff to finalize the agreement to meet project start obligations tied to developer timelines; the engineer's estimate was $4,066,000.
The full story
Council reviewed bids Nov. 4 for the West Interceptor Segment 2 project and authorized staff to accept the low bidder and finalize the contract.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
or
Free account
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →