Council Authorizes Staff to Finalize West Interceptor Segment 2 Contract
Nov 5, 2025
Council accepted the low bid from Guijo Construction ($3,315,089.38) for West Interceptor Segment 2 and authorized staff to finalize the agreement to meet project start obligations tied to developer timelines; the engineer's estimate was $4,066,000.
The full story
Council reviewed bids Nov. 4 for the West Interceptor Segment 2 project and authorized staff to accept the low bidder and finalize the contract.