Deerfield staff brief board on water-main break under creek; directional drilling estimate $30,000
Summary
Public works informed the Deerfield board that a water-main crossing beneath a local creek broke; staff said residents were not without water, fire hydrants remain operational, directional drilling is required to replace the crossing, and an initial drilling-only estimate is about $30,000 with total repair costs likely under $100,000; staff will return with full pricing in 2–4 weeks.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Public works staff briefed the Village of Deerfield Board of Trustees on April 21 about a water-main break that occurred under a creek near Illinois Trail and Cherry Court.
Bob Phillips (public works) said crews capped and isolated the affected section so no residents are out of water and fire hydrants remain functional. He told trustees the crossing will require directional drilling to replace the main—an open-cut excavation through the creek is not feasible—and the village has a directional-drill-only estimate of about $30,000 (materials and labor not included). Phillips said staff are obtaining additional bids and expect to return to the board with more complete pricing and a recommended plan within roughly two to four weeks.
Phillips said the affected pipe dates to the 1960s and that construction activity on nearby Hazel Avenue, plus pressure changes in the system (a "water hammer" effect), could have contributed to the failure. He said prior crossings beneath creeks have failed before and that the village—s repair work will seek to restore normal circulation and avoid dead ends in the system.
Trustees praised staff for the response and asked staff to investigate whether adjacent sections of main need replacement; staff said they would follow up and include required pricing and scope when they return to the board.
Provenance: briefing begins SEG 867 and discussion continues through SEG 1030; staff cited directional drilling price and an estimated total repair cost.