Glendale council approves CIP changes: delay water‑main program, buy two dump trucks and increase HVAC funds

Common Council of the City of Glendale · January 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staffers told the council they will delay the water‑main replacement program by one year to pursue longer low‑interest financing; the council approved amendments to buy two 5‑ton dump trucks in 2026 (budget increased to $352,000) and to raise the HVAC replacement estimate to $470,000.

City staff presented an update to the 2026 Capital Improvement Plan and proposed budget amendments, and the Common Council approved the changes.

Staff said nine water main breaks had occurred so far this year and that, after reexamining the water fund (which had gone nine years without a rate increase), they recommended delaying the water main replacement program by one year and planning to use a 20‑year low interest loan in future years to reduce annual debt service. Staff explained a 10‑year loan at a 5% rate would cost roughly $635,000 in interest over the term with annual payment around $288,000, while a 20‑year loan at an estimated 2.5% would lower annual payments.

Staff also asked to accelerate the purchase of two 5‑ton dump trucks into 2026, increasing the line item from $205,000 to $352,000 because one truck suffered catastrophic failure and another became available sooner. Council approved the amendment to ensure fleet continuity during winter operations. Finally, staff recommended and council approved an amendment to increase the HVAC replacement budget to $470,000 (engineering updated the construction estimate). The council moved and approved the CIP amendments.