Courthouse phase‑2 bids top estimates; consultants recommend rebidding electrical package while finance models options
Feb 17, 2026
Bids for the courthouse phase‑2 remodel came in roughly $206,000 over estimate with the electrical package about $420,000 higher than the prior low bid; consultants recommended rebidding the electrical package, and county staff were asked to model financing options including ARPA, bond proceeds, local option sales tax and possible urban‑renewal extension.
The full story
Consultants presented bid results for phase‑2 of the county courthouse remodel and recommended rebidding the electrical package to increase competition after the package returned substantially above the project estimate.