Council approves $22,434 change order and $16,000 contract amendment for Cookeville water‑plant standby power work

Cookeville City Council · February 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council authorized Change Order No. 2 (adding SCADA monitoring, a remote enunciator panel, security lighting and abandoned wiring) for $22,434 and approved Amendment No. 1 to the engineering services agreement for an additional $16,000 to cover added construction administration on the standby power project; both actions carry a 5% city share under grant coverage.

Mister Turner, speaking for city utilities, presented two related items for the Cookeville Water Plant’s standby power project. Change Order No. 2 adds SCADA monitoring, a remote enunciator panel, security lighting and the abandonment of some poles and wiring; Turner said some of those items should have been in the original contract and others are added, producing a net increase of $22,434 to the contract. Turner said these added costs are covered by grant funding and the city’s portion is 5%.

Turner also presented Amendment No. 1 to the engineering services agreement to cover additional construction administration and inspector time related to the standby power work, adding $16,000 to the contract. He said the amendment shifts some items within the contract total and reflects additional inspection/administration expenses.

Vice Mayor Eldridge moved the motions to authorize the city manager to execute Change Order No. 2 and to approve Amendment No. 1 to the engineering services agreement; council approved both motions by 4–0 vote.

The council record shows both items were recommended for approval by staff and that the city’s local share under the grant is 5%; staff noted timing and administration adjustments but did not identify major scope changes beyond the added equipment and administrative time.