Committee recommends Planning Commission accept Redtail Ridge Phase 2 layout changes

Apr 8, 2024

The committee recommended that the Planning Commission accept proposed changes to the Redtail Ridge Phase 2 plat—tighter intersection spacing on Bellefontaine, S‑curve alignments, and a pedestrian connection—after weighing stormwater, lot loss and cost tradeoffs.

The full story

The Public Works Committee recommended that the Planning Commission accept several proposed changes to the Redtail Ridge Phase 2 final plat, including slightly reduced spacing at three intersections along Bellefontaine, alignment shifts that introduce S‑curves on neighborhood streets, and a pedestrian connection to a public park.