Commissioners hear Tallgrass pipeline progress: easements obtained, corridor work largely complete
May 21, 2025
May 21, 2025
County officials reported Tallgrass has acquired voluntary easements across the county and is well along in construction—82% vegetation cleared, 68% graded, 9% pipe laid and 5% boring—with the roads department coordinating haul routes; commissioners asked the company to address reports of aggressive driving by contractors.
The full story
York County commissioners heard an update on Tallgrass pipeline construction through the county and were told the project is substantially advanced in several work phases.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
or
Free account
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →