County officials reported Tallgrass has acquired voluntary easements across the county and is well along in construction—82% vegetation cleared, 68% graded, 9% pipe laid and 5% boring—with the roads department coordinating haul routes; commissioners asked the company to address reports of aggressive driving by contractors.

The full story

York County commissioners heard an update on Tallgrass pipeline construction through the county and were told the project is substantially advanced in several work phases.