Board approves courthouse change order, chiller contract and HVAC engineering work
Summary
Hall County approved change order #5 for courthouse work (including waterproofing and additional fire alarm panel), awarded a $551,300 contract for a chiller and approved engineering services for an HVAC project at the corrections facility (5–2 votes on several items).
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Hall County Board approved a series of facilities and construction actions at its December meeting, including change order #5 for the courthouse project, a chiller contract and HVAC engineering services for the corrections facility.
Facilities director (Speaker 11) outlined change order #5, which included waterproofing approved at a prior meeting, a required additional fire alarm panel (requested by the fire marshal), hollow‑core infill that was omitted from earlier plans and adjustments to fiber routing between buildings after a contractor cut an existing run. The board approved change order #5 by a vote of 5 yes, 2 no.
The board also approved a contract with Russ and Campus Service for a chiller on the Whitney project for $551,300; that contract passed 5 yes, 2 no after discussion about bid completeness and items that had been omitted from the initial bid package but included in the total price.
Separately, commissioners approved engineering services with Strategic Design for the Hall County corrections HVAC project. Commissioners and several speakers discussed concern over limited bidders on large projects, the need to keep specifications sufficiently open to encourage competition and the large cost implications for postponing projects. The engineering services motion passed 5 yes, 2 no.
Commissioners instructed staff to continue outreach to potential bidders, provide clearer specifications where possible and present the financial impact on the courthouse and corrections budgets when final bids are sought.