DOT‑funded Douglas Ferry improvements 58% complete; county asked to approve resolution

Feb 10, 2026

Engineering staff told the board that the Douglas Ferry Road improvements are about 58% complete with drainage mostly finished, that DOT provided additional funds requiring a resolution to accompany a supplemental agreement (G3148), and that paving and base repairs are underway with a current final completion target in April.

The full story

Engineering staff provided a project update on Douglas Ferry Road and requested the board provide a resolution to accompany a supplemental agreement with the Department of Transportation.