During the same session, the court approved an emergency services MOU with High Point Charities, accepted a Walmart donation to fund a tornado siren, authorized 911 grant applications, approved a law enforcement grant application, contracted paving inspectors, reduced developer sureties and approved several personnel hires.
Get email alerts on the County Operations topic
No spam. Unsubscribe anytime.
At its March session the Oldham County Fiscal Court approved multiple administrative and operational items alongside the rezoning decision.
Emergency Management director Zach Wilt presented an MOU with High Point Charitable Service to supply food and support during disasters; the court approved entering the agreement and asked that the MOU header be updated to show Oldham County Fiscal Court as the contracting party.
Wilt also outlined a Federal Signal tornado siren procurement plan funded partly by a $30,000 donation from Walmart; Crestwood pledged up to roughly $14,800 to cover installation labor. The court authorized signing the quote and directed staff to finalize interlocal arrangements for installation and maintenance (the county will adopt maintenance responsibility; the siren carries a five‑year manufacturer warranty).
Greg Beck, director of Oldham County Dispatch, secured court approval to submit grant applications to the Kentucky 911 Services Board for both a console upgrade (approx. $129,000 project with a 10% county match budgeted next fiscal year) and two additional portable 'phone‑in‑a‑bag' dispatch units (project ~$70,200; county portion ~$7,020). Magistrates approved applying and authorized the judge to sign required documents.
The court also authorized submission of a Kentucky Office of Homeland Security LEPP grant application (law enforcement protection program) to replace and equip department firearms, helmets and ammunition (estimated request ~$202,104.76). The application is reimbursable if awarded.
County engineer Jim Silbin presented a short‑term contract with AECOM to provide two paving inspectors for the remaining paving groups; the court authorized the contract to ensure inspection capacity before fiscal‑year end. Magistrates discussed funding sources and potential impact to the paving budget but approved execution of the contract.
The court approved recommended reductions in three performance surety bonds for local subdivisions (L'Esprey Sections 3A/3B; Royal Oaks Section 1) after reviews showed infrastructure completion sufficient to justify retained balances.
Finally, the court approved several personnel actions — hiring Lynn Robinson as a financial management specialist, rehiring Paul Stoops as building inspector and hiring a seasonal parks worker — and approved other routine consent items before adjourning.
Next steps: Emergency Management will finalize MOU and donor agreements; Dispatch will submit grant applications ahead of deadlines, and the county engineer will execute the AECOM contract and release surety funds as appropriate.