McKinney council approves $7.4M budget shift and contracts to advance airport east‑side work
Summary
The McKinney City Council approved an ordinance shifting $7.4 million in EDC funds and authorized construction and consulting contracts to advance the McKinney National Airport Eastside development, including Taxiway Charlie and an FM 546 roundabout; staff said the phase will cost about $20.7 million.
Get email alerts on the Airport Development topic
No spam. Unsubscribe anytime.
The McKinney City Council on Dec. 17 approved an ordinance moving $7,400,000 of Economic Development Corporation funding into the McKinney National Airport Eastside development and authorized related construction and consulting agreements to begin the next phase of work.
Ken Carley, airport director, told the council the approvals cover Taxiway Charlie (the parallel taxiway on the airport’s east side), an FM 546 roundabout to bring vehicle traffic to the site, the apron and parking infrastructure, and terminal support work. “Tonight on the agenda, we've got four items, enabling the next phase of construction for the terminal project,” Carley said.
Carley said the EDC has allocated $22.4 million to the project; the council previously moved $15 million into the project and the $7.4 million approved Dec. 17 completes that EDC commitment. He reported the construction contract with Mario Sinicola and Sons Excavating is the low bid at $17,600,000 (including about 10% contingency), Garver’s amended contract for construction administration and terminal area services is $2,900,000, and a Terracon agreement for materials testing is about $158,000. Carley summarized the phase cost as roughly $20,700,000.
Carley also said the city has executed a use and lease agreement with Velo Airlines that will make that carrier the terminal’s first partner and set terms to discuss service with other airlines.
Councilman Cloutier moved to approve the budget amendment and ordinance; Mayor Pro Tem Feltes seconded, and the chair announced the motion carried. The transcript records the approvals but did not include a roll‑call tally for the airport items.
What happens next: staff will execute the authorized contracts and proceed with construction administration and materials testing for the east‑side phase. Carley said project photos and a status update will be provided at next month’s meeting.
Budget and contracts approved (as described to council): - Ordinance to amend FY25–26 budget to allocate $7,400,000 of EDC funds to the airport project (mover: Councilman Cloutier; second: Mayor Pro Tem Feltes; outcome: approved). - Resolution authorizing agreement with Terracon Consultants for materials testing and observation (outcome: approved). - Resolution authorizing amendment with Garver LLC for construction administration and terminal area services (outcome: approved). - Resolution authorizing contract with Mario Sinicola and Sons Excavating for construction of Eastside infrastructure (outcome: approved).
Sources and provenance: presentation and figures reported by Ken Carley, Airport Director (transcript SEG 406–492; motion and approvals SEG 499–558).