Union County reviews stoplight options and posts new bridge weight limits after inspection
Summary
Highway Superintendent Jerry Buum told commissioners about patching plans, message-board rentals (~$8,000/month), temporary stoplight/detour options estimated at $10,000–$15,000 per site per month, and permanent signal costs (~$120,000 per intersection); several bridges received or retained weight restrictions after Ulteig inspections.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Jerry Buum, Union County highway superintendent, briefed the commissioners Aug. 20 on road and bridge operations and traffic-control options.
Buum said paver patching is planned for CR #4 and CR #27, and that message boards are in place on CR #1 and CR 1B at an estimated $8,000 per month. The board discussed temporary traffic-signal options to manage detours: Traffic Solutions Inc. quoted about $15,000 per site per month (for two sites), while Dakota Traffic’s estimate was roughly $10,000 per site per month; total temporary costs were described as approximately $20,000–$30,000 per month for three to nine months depending on project duration. Buum said permanent signal installation from Nystrom Electric is estimated at $120,000 per intersection, with the county responsible for ongoing electric bills.
On bridges, Buum reviewed inspection findings: bridge 64-042-050 remains posted at a 12-ton single-axle and 20-ton combination limit; bridge 64-120-062 has been posted to a 6-ton limit after Ulteig found a crushed cap; bridge 64-020-141 will be posted 12-ton single-axle and 20-ton combination. Hollaway Construction was compiling budget estimates for needed work.
Why it matters: The temporary-signal and message-board cost estimates have immediate budget implications for managing detours; posted bridge weight limits affect local and commercial traffic. The board did not record a separate formal vote on these highway cost options during the Aug. 20 meeting.