City council approved awarding RFB2026-045 (pipe-bursting/horizontal directional drilling) to Murphy Pipeline Contractor for $11,153,320 to continue phased water-infrastructure replacement; staff said phase one is nearing completion and phase two is planned.
The full story
LAREDO, Texas — The City Council on March 16 approved awarding service contract RFB2026-045 to Murphy Pipeline Contractor (Sunrise, Florida) for a waterworks infrastructure project that will replace aging pipe via pipe bursting and horizontal directional drilling. The contract amount is $11,153,320 and the estimated completion time is 220 working days.