Lyon County moves Bridge 71W up in Five‑Year Construction Program; engineer reports hiring pause after resignation
Mar 10, 2026
Mar 10, 2026
County Engineer Daryl Albertson told the Board the Bridge 71W ER project will be moved from FY2028 and scheduled to be let by October; the Board approved the Five‑Year Program amendment and noted a truck driver resigned, with the department pausing replacement hiring.
The full story
County Engineer Daryl Albertson told the Board on March 10 that the Bridge 71W ER project will be moved forward from fiscal year 2028 and scheduled to be let by October of this year. The Board approved the amendment to the Five‑Year Construction Program and authorized the chairman to sign (motion by Altena, second by Scholten).