Get email alerts on the Wastewater Infrastructure topic
No spam. Unsubscribe anytime.
Committee awards $1.6M MCC replacement contract for Appleton wastewater plant, staff say CIP covers phases
Summary
The finance committee awarded phase 1 of the MCC replacement at the Appleton Wastewater Treatment Plant to Vanner Electric for $1,605,450 (10% contingency; project total not to exceed $1,765,995). Deputy Director Gruffert said the 2025 CIP has $3.8 million and staff expect funds for both phases.
Get email alerts on the Wastewater Infrastructure topic
No spam. Unsubscribe anytime.
The Appleton finance committee on Dec. 8 voted 4-0 to award phase 1 of the motor control center (MCC) replacement at the Appleton Wastewater Treatment Plant to Vanner Electric Company for $1,605,450, with a 10% contingency that yields a project cap of $1,765,995.
Alder Hartzheim asked whether the city had adequate budget capacity for the work and whether other project costs could erode the allocation. "There's $3,800,000 in the CIP for 2025," Deputy Director Gruffert said, adding the city expects to carry a balance into 2026 for phase 2. "We're comfortable that there'll be enough money to do both phases," Gruffert told the committee.
The item was moved, seconded and approved unanimously. The contract award authorizes staff to proceed with phase 1 under the contracted terms; staff did not record further scope changes in the meeting.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.
