Commission reviews generator projects, approves contracts for critical facilities

Mobile County Commission · March 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commission reviewed multiple generator and HVAC-related contract amendments, including a change order for an Africa Town Hall generator, an amended Smith Mechanical design contract for Mobile Government Plaza cooling, and a proposed $382,000 assignment for architects to handle emergency-generator installations at critical county facilities.

County staff presented a series of contract updates and change orders addressing emergency power and mechanical systems across county facilities.

The Clerk outlined a change order with Harris Contracting Services for installation of an emergency generator at Africa Town Hall and the Mobile Food Bank, reporting a $5,523 decrease that produced a new contract total of $161,484. Commissioners noted the county had been awaiting that generator for roughly two years.

Separately, staff described Amendment No. 1 with Smith Mechanical Consulting and Design to expand services for the Mobile Government Plaza cooling-tower replacement, adding mechanical and structural design for a maintenance platform and auxiliary chilled-water piping; that modification results in a net contract decrease of $15,000 to a new total of $199,751 as presented.

The Clerk also recommended assigning P, H & J Architects to provide design, bidding and project administration for installation of emergency generators at critical Mobile County facilities with a proposed amount of $382,000. Commissioners asked how many facilities would be included; staff deferred specifics and said they would provide details to commissioners.

Why it matters: Emergency generators and reliable cooling systems are critical for public-facing county facilities and social-service operations. Contract amendments and design assignments authorize staff to proceed with procurement and project delivery tasks.

What’s next: Staff will provide facility counts and scheduling details for the $382,000 generator architectural work and will advertise or execute change orders per normal procurement processes.