Castleberry ISD bond program on schedule, construction team reports 60–62% complete
Summary
The district’s construction update said the 2024 high‑school bond project is roughly 60–62% complete, mechanical startup and furniture installation are scheduled for summer, and staff plan to standardize new technologies districtwide to reduce long‑term operating costs.
Get email alerts on the Bond Program topic
No spam. Unsubscribe anytime.
A monthly construction update presented to the Castleberry Independent School District board reported that the 2024 high‑school bond program is moving on schedule and within budget, with the project about 60–62 percent complete and payouts of roughly 55–56 percent so far.
The presenter said the project team drilled the first foundation pier on Feb. 22, 2025, and that renovations will continue through the summer while new construction runs into January, with no current reason to expect significant schedule slippage. Site work described at the meeting included transformer installation, mechanical equipment sequencing required for controlled finishes, front‑entrance grading, and upcoming FF&E (furniture, fixtures and equipment) installation.
Photos shown to the board highlighted learning stairs, connector areas, and progress on façade and glazing. The presenter also described district plans to standardize HVAC and building‑controls technology being piloted at the new high school so that maintenance and operating costs can be reduced when systems are replicated across roughly 75 percent of district buildings.
From a financial perspective, the presenter said the project remains within the guaranteed maximum price (GMP) and that about 62 percent of construction costs remain in the work‑in‑progress pipeline (finishes and FF&E). The team also noted that about a 4 percentage‑point difference in completion equates to roughly $2–2.5 million in spend pacing at this stage.
The board asked no formal questions that changed the schedule; the presenter said Centrix (vendor/consultant) and third‑party engineering reviews would inform any final scope changes and legal review of contract terms is underway.