County reports 75% completion on Integrated Water Master Plan; contingency partially spent
Mar 11, 2026
Utility staff told commissioners the integrated water master plan is about 75% complete, targeted for delivery mid‑July 2026, and that roughly $272,000 of a $742,000 contingency has been authorized; additional studies (Sebastian septic‑to‑sewer feasibility and a pump‑station conversion) are underway.
The full story
Howard Richards, manager of capital projects for the Department of Utility Services, briefed commissioners on the Integrated Water Master Plan, a HDR Engineering project designed to address growth, aging infrastructure and regulatory change over a 20‑year planning horizon.