Committee approves up to $875,000 for right-of-way acquisition on Green Street Mobility project

City of Roswell Committee · January 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Roswell staff described the Green Street Mobility project (multiuse trail, one-way conversion, buried utilities) and the committee unanimously approved blanket authorization to acquire rights-of-way and options for 16 parcels up to $875,000.

The Roswell committee approved Jan. 27 a not-to-exceed $875,000 authorization for right-of-way acquisition services and acceptance of right-of-way options for phase one of the Green Street Mobility project.

"This project will construct an 8 to 10 foot multi use trail along Green Street from State Route 9 to Cherry Way," said Mr. Nicholas during the presentation, describing plans to convert Green Street to one-way southbound, convert Plum Tree Street to a pedestrian path and place aerial utilities underground. Staff said 16 parcels will be impacted and the $875,000 figure is based on appraisal estimates plus contingency.

Committee members had no questions and the motion to approve the blanket right-of-way acquisition authorization (not to exceed $875,000) passed unanimously. Staff said funding is available in the project account and that any amount above the not-to-exceed figure would be returned to council for action.

Next steps: staff will proceed with appraisal and acquisition outreach for the affected parcels and will return to council if additional funding is needed.