Summary

Council directed staff to put 'proposal 2' — drainage and culvert work aligned with the 2026 road maintenance plan — out to bid, adding several specific sites for itemized pricing; staff said the city's MS4 plan has been submitted to TCEQ and mapping of citywide drains will take 4–6 months.

Bulverde — The City Council voted to solicit bids for a prioritized culvert and drainage maintenance package that aligns with the city’s 2026 road maintenance plan and to add several additional sites for separate, itemized pricing.

Staff told council the city submitted a Special Environmental Project (SEP) and its MS4 stormwater plan to the Texas Commission on Environmental Quality and is awaiting a final permit number before posting the plan publicly. “The MS4 plan itself, I think it's a 4-year plan,” a staff member said, describing the multi-year compliance and reporting schedule.

Council members emphasized the need to avoid duplicative contractor mobilizations and to obtain itemized bids so the city can compare line items and prioritize critical replacements. Staff estimated full culvert replacements would likely cost roughly $15,000–$25,000 each and noted the city currently has about $100,000 available in the line item discussed. The staff member said mapping and compiling a citywide inventory of culverts and drains will take an estimated 4–6 months.

Motion and scope: The council’s motion sent proposal 2 to bid and added the line items the motion named, including Old Burby/3077 and Deerfield Terrace, with direction to include itemized pricing. The mayor moved the motion and the council approved it by voice vote.

Why it matters: Coordinating drainage repairs with planned road work can reduce repeated street disruptions and contractor mobilization costs. Several council members pushed to prioritize high-risk or road-adjacent culverts to avoid having roads torn up twice.

Next steps: Staff will prepare the bid package with itemized line items, seek competitive bids and return to council with the results and recommended priorities. Council asked staff to examine contract language to ensure contractors coordinate with road maintenance schedules.