Invenergy updates Parmer County on Lazbuddie I and II wind projects; blade shipments delayed
Summary
Invenergy representative Alex Chandler told the commissioners that Lazbuddie I remains on track for an August 2026 online date, Lazbuddie II is in the construction planning phase with an expected 2027 online start, and that turbine blade shipments have been delayed.
Get email alerts on the Energy topic
No spam. Unsubscribe anytime.
An Invenergy representative updated the Parmer County Commissioners on the Lazbuddie I and II wind projects during the Jan. 13 meeting.
Alex Chandler said Lazbuddie I remains on track for an August 2026 online date. Chandler said Lazbuddie II is currently in the construction planning phase with an approximate online start in 2027. He added that the project has experienced a shipping delay in receiving turbine blades for the towers, which could affect schedule if not resolved.
The update was informational; no county action or vote was recorded on the projects. Chandler and county officials framed the remarks as a status report. The transcript does not include contractual terms, local permitting details or assurances about mitigation of the blade‑shipment delay.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.