Planning commission reports reservoir construction under way after approving conditional use permit
Apr 22, 2026
Apr 22, 2026
City staff told the commission that an approved conditional use permit for a new reservoir and pump station at Southwest 108th has foundation poured and walls expected by April 30; staff said the permit was unanimously approved by the commission.
The full story
City planning staff reported that a conditional use permit for a new water reservoir and pump station at Southwest 108th has moved into construction after the planning commission's approval.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
or
Free account
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →