Council hears progress on Clermont Drive, Lamar extension and Kirkpatrick change order
Summary
Staff updated council on thoroughfare planning: Clermont Drive is 30% in design (design complete Feb 2027), Lamar extension is in right‑of‑way acquisition (60% plans) with owners being negotiated, and Kirkpatrick Drive requires a ~$237,000 change order for uncovered quantities but remains under budget.
Public‑works staff briefed council on several transportation projects that the council prioritized at last year’s retreat.
Clermont Drive: staff said the project is being designed as a four‑lane divided arterial of about 1.5 miles and is at roughly 30% design completion; design is scheduled to complete in February 2027. Staff said…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat