Rockwall County approves change order No. 7 for sheriff's office IT work

Rockwall County Commissioners Court · December 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners approved prime contract change order No. 7 with SCI Construction to cover low-voltage/IT work in the sheriff's office renovation. The item adds about $59,000 to contractor contingency and raises expected low-voltage costs to roughly $120,000; the court said it will use the builder's contingency rather than the IT allowance.

The Rockwall County Commissioners Court unanimously approved prime contract change order No. 7 to the agreement with SCI Construction for low-voltage work in the Rockwall County Sheriff’s Office renovation.

Commissioner Stacy summarized the change order, telling the court the work consolidates the county’s IT infrastructure into a single server/IT room and requires extensive fiber and wiring runs. “This is adding, $59,000 into the contingency,” Stacy said, and noted earlier estimates in the GMP anticipated about $68,000 for low-voltage work while the change order brings the likely cost closer to $120,000–$123,000.

Stacy told the court the project would use the builder’s contingency for this expense and would not yet draw on the $120,000 IT allowance set aside for unexpected IT work. The commissioner said more potential change orders (PCOs) may come once phase 2 proceeds and the IT room build-out begins.

The judge asked for questions; none were raised. Commissioner Stacy moved to approve the change order; the motion was seconded and passed 5–0.

Why it matters: consolidating IT systems into a dedicated server room is intended to improve efficiency and reduce long-term operating costs, but the near-term contract adjustment increases project contingency use and raises the county’s near-term construction spending profile.

Next steps: the construction team will continue coordination on phase 2 IT build-out; any further owner-directed change orders will be addressed in future court actions.