Justice Center project 87% complete after $1.8M payout, engineer says

Apr 7, 2026

John A. Hernandez reported the Justice Center construction is about 87% complete after an approximately $1.8 million monthly payout; elevators are being assembled, first-floor furniture installation is tentatively scheduled for May 19 and the third floor remains the project's critical path.

The full story

John A. Hernandez, P.E., the county project engineer, told the San Patricio County Commissioners Court that the Justice Center construction project is roughly 87% complete following an approximately $1.8 million progress payment this month. "The monthly payout for this month is approximately 1,800,000 and that'll bring the project completion to about 87% complete," Hernandez said.