Joint Appropriations committee approves Richmond Lake Dam reporting schedule

May 1, 2026

The Joint Committee on Appropriations approved a letter of intent requiring recurring progress updates on the Richmond Lake Dam project; the commissioner said work is slated to mobilize May 4 and the project could finish in two construction seasons, with a contingency to July 2028.

The full story

The Joint Committee on Appropriations on April 30 approved a letter of intent asking for recurring progress updates on the Richmond Lake Dam project.