Citizen Portal
Sign In

Get AI Briefings, Transcripts & Alerts on Local & National Government Meetings — Forever.

Board is presented with $43,260.47 change order for Lawrence Education Center renovation

Springfield SD 186 Board of Education · May 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A change order of $43,260.47 to replace older breaker boxes at Lawrence Education Center was presented; contractors discovered older pushmatic breaker boxes the board was told are a safety concern and the project remains on track for July completion.

Board project staff presented change order number 2 for Lawrence Education Center on May 4, asking the board to authorize $43,260.47 to Johnco to replace aging breaker boxes found during renovation work.

"Those type of breaker boxes tend to not trip, which is a safety hazard," Carlson told the board, explaining the work is necessary while the renovation is underway. Carlson said the elevator is being installed and restrooms are being drywalled; the project timeline remains on track with an estimated July completion and plans to have students in the building in August.

Board members asked a few clarifying questions about timelines and future plans for the existing Douglas facility; Carlson said a roof replacement for the old Douglas building is planned using Health Life Safety funds and that decisions about Douglas's long-term use will come later.

Why it matters: The work responds to a discovered safety hazard and is budgeted as a change order to an active renovation project. Updating electrical panels is intended to meet safety standards and keep the project on schedule for fall occupancy.

What happens next: The superintendent recommended the resolution and the board received the change order presentation. The transcript does not record a separate vote on this specific change order within the posted segments.