Commissioners approve two change orders, adding about $75,265 to Rattlesnake water contract

Nov 24, 2025

The board approved Change Orders No. 5 and No. 6 for the Mid Atlantic Storage Systems contract on the Rattlesnake Water System, increasing the contract by $70,900 and $4,365 respectively and changing the revised contract price to $8,959,211.57.

The full story

The Fayette County commissioners approved two change orders for the Mid Atlantic Storage Systems contract on the Rattlesnake Water System Improvements (Contract B ' Headworks).