Fayette County approves $26,558 change order for Rattlesnake water project
Nov 17, 2025
Nov 17, 2025
The Fayette County commissioners approved Change Order No. 7 for the Rattlesnake Water System Improvements on Nov. 17, adding $26,558 to the contract and raising the total to $8,985,769.57; the time for completion was unchanged.
The full story
The Board of Fayette County Commissioners on Nov. 17 approved Change Order No. 7 for the Rattlesnake Water System Improvements, adding $26,558 to the existing contract for Contract B (Headworks) with Mid Atlantic Storage Systems. The change order itemizes engineer and design office hours, motor starters provided by CT Electric, and temporary laboratory power, and leaves the project schedule unchanged.