Commission approves $180,000 microsurfacing contract to save on patching costs
Summary
The board approved piggybacking on Leavenworth County pricing to microsurface three miles at $60,000 per mile (total $180,000), which Road & Bridge said would save about $10,000 compared with separate patching and chip-and-seal work.
Get email alerts on the Road Maintenance topic
No spam. Unsubscribe anytime.
The Atchison County commissioners approved a proposal to piggyback Leavenworth County's pricing and hire Vance Brothers to microsurface three miles at $60,000 per mile, for a total of $180,000.
Road & Bridge staff said microsurfacing the designated chip-and-seal roads would save the county approximately $10,000 compared with the combined cost of extensive patching and chip-and-seal operations. "We're saving $10,000 by doing the microsurfacing," staff said during the presentation.
Commissioners moved, seconded and approved the proposal 3-0. Road & Bridge will finalize purchase orders and scheduling with the contractor.
Next steps: Staff will sign the piggyback agreement, finalize a purchase order, and schedule microsurfacing work when weather and crews allow.