Committee approves transfer from UWMWEC electrical project to cover remodeling change orders
Summary
The Public Works Committee approved a resolution to amend the capital improvement plan and transfer approximately $444,000 from the under-budget UWMWEC electrical upgrade project to cover change orders, asbestos abatement and added security work in a master plan remodeling project.
The Washington County Public Works Committee approved a 2025 resolution to amend the capital improvement plan and transfer funds from the UWMWEC electrical upgrade project to cover increased costs on the county’s master plan remodeling project.
Scott, speaking to the committee, outlined reasons for the funding request: a significant increase in the card-access and security system scope, unexpected asbestos testing and abatement, approximately 30 change orders to date tied to working in an older building, contaminated soil discovered near the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat