Brainerd City committee approved the final payment of $18,170.95 for the M Street outfall repair near Evergreen Cemetery; staff said the work was reviewed by the property owner and engineering firm WSB and the payment is about 3% under the original bid.

The full story

Brainerd City’s Safety & Public Works Committee on Jan. 20 approved a final pay request for the M Street Outfall improvement, recommending a payment of $18,170.95 to complete work on the outfall near Evergreen Cemetery and the Bick property. Staff said the Bick property owner reviewed the work and described it as "project is good," and that engineering firm WSB also approved the completed work.