Committee approves third 30-day permit extension and $100,000 additional escrow for downtown BOA building purchase

Apr 30, 2026

After a design and schedule update from Klein Sweeney Associates, the Property Management Committee voted to exercise a third 30-day extension and add $100,000 to the county's nonrefundable escrow (bringing it to $450,000) for a proposed downtown building purchase; the motion passed 5-2 on roll call.

The full story

Bart Klein of Klein Sweeney Associates briefed the Property Management Committee on design-development work for the BOA building, noting that American Constructors is serving as construction-manager-at-risk and that staff are confirming site and envelope conditions ahead of final buyout estimates.