Santa Rita board hears update on modernization, TIP facility and developer-fee study

Santa Rita Union School Board · April 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff told the board the phase-one modular classrooms are now on schedule for late-year occupancy, the Monterey County TIP and Head Start space at La Joya is under construction with a Dec. 31 target, and a developer-fee study and modernization eligibility worksheets will be updated this summer.

District staff updated the Santa Rita Union School Board on the progress of multiple modernization projects, a new Therapeutic Intervention Program (TIP) facility shared with Monterey County Office of Education (MCOE) Head Start, and an upcoming developer-fee study.

The board was told that phase-one modular sections have been delivered and craned onto foundations, and that weather-permitting crews will complete exterior finishes, interior systems and inspections before furniture installation. Staff said the contractor is aiming for a November–December occupancy window but cautioned timelines remain subject to change.

Staff thanked voters for Measure R funding that is enabling the projects and said the district will submit completed projects to the state for reimbursement, which will fund subsequent modernization phases. The district also described a coordinated schedule at La Joya so the TIP/Head Start construction (which began March 30 with site testing and soil work) completes before La Joya’s own modernization starts, avoiding concurrent heavy-construction activity on the same campus.

The TIP facility, which district staff said will include offices, restrooms, a small parking and bus turnaround and up to five classrooms with a dedicated entrance, is intended to serve TIP students countywide while offering scheduled gated access to La Joya playfields. Staff gave a targeted completion date of Dec. 31 for TIP’s construction so La Joya’s modernization can commence afterward.

On funding and fees, staff previewed a developer-fee study that will be updated in July to support level-two or level-three fee calculations as needed. The district recited state-set level-one fee amounts of $5.38 per residential square foot and $0.87 per commercial square foot, and discussed the level-two/level-three formulas; a current level-three example figure mentioned in the presentation was $14.54 per square foot. Staff said they will return with a resolution to start the developer-fee process and present the final plan in July.

The board also heard about operational improvements: the district reported a 92% completion rate on about 1,030 work orders this fiscal year after troubleshooting notification routing in its SchoolDude maintenance system, and staff said they are evaluating a more comprehensive multi-department system for implementation in roughly a year.

The presentation closed with plans to publicize progress to voters and community members so Measure R expenditures are transparent and the public can follow project timelines and reimbursements.