ODOT project halted until county, state settle who pays roughly $439,000 water‑line relocation
Feb 11, 2025
ODOT and county engineers told Commissioners that a planned intersection and sidewalk package near Howland Corners is paused because a water line in state right‑of‑way must be relocated; initial estimates put the county share at about $439,000, but staff said design savings could reduce that by roughly $200,000.
The full story
Chad Rut, capital programs administrator for ODOT District 4, briefed the Trumbull County Commissioners on a multi‑site road and safety package that includes a diverging‑diamond interchange already under construction and a separate intersection/sidewalk/signal project at 46 and Market Street in Howland Corners. Rut said crews must move a water line inside ODOT’s right‑of‑way because state separation standards require greater distance between the existing water and planned sewer improvements.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →