Board approves phasing changes for Brain Park redevelopment and awards wet detention basin contract

Mar 4, 2026

The Board of Public Works approved a re-sequencing of Brain Park projects—advancing the restroom to 2026 and deferring the playground and pavilion to 2027—to resolve site conflicts and improve utility coordination, and authorized a $583,640.30 contract for a wet detention basin to meet stormwater phosphorus requirements.

The full story

Justin Caspersonson, the city’s park and recreation director, told the Board of Public Works the department is asking the board to approve a re-sequencing of the Brain Park redevelopment that advances the restroom construction from 2027 to 2026 and defers the playground and pavilion from 2026 to 2027.