County opens bids for $711,684 chiller replacement at administration building

Richland County Board of Commissioners · May 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At a public bid opening the county received multiple bids for a chiller replacement project budgeted at $711,684; staff said they will review submissions and return with a recommendation, with completion expected in about 220 calendar days after award.

Richland County officials opened bids May 14 for a chiller replacement at the county administration building, a capital project the county budgeted at $711,684.

Craig Christie, representing the project team, described the work as a 215-ton split-system installation with associated roof structural work. "It'll be 215 tons of cooling nominal ... we've had a walk through ... and approximately 220 calendar days for completion of the project once it's awarded," Christie said. He told commissioners no long-lead items were identified.

Bids were received from Stevens Construction and Standard Plumbing & Heating, among others; county staff said they will review the paperwork, perform due diligence and then consult with commissioners to award the contract. The meeting included a public reading of bid submissions and brief questions about bid bonds and line-item confirmation.

Commissioners recessed for additional agenda items and said they would return with a recommendation after staff review. No award was made on May 14.

The project team noted plans for crane placement and roof work when unit delivery occurs; the county estimated roughly seven months for construction and commissioning, subject to award and vendor lead times.