Resiliency staff update: flood projects advance, Green Tier reporting is a heavy data lift

Apr 20, 2026

The resiliency coordinator reported 90% engineering drafts for a park flood project, East River/Emily Park construction slated for next spring pending conditions, a $900,000 Connect the Bay engineering award, and described Green Tier reporting as a large spreadsheet effort that may benefit from intern support to create shareable year-over-year outputs.

The full story

Resiliency staff provided project and reporting updates, including progress on flood resiliency designs, grant applications, and a discussion about the burden of Green Tier reporting and options for turning spreadsheet data into shareable information.