CUSD 300 seeks HVAC BAS standardization at Parkview, multiple roofing and safety upgrades
Feb 10, 2026
Feb 10, 2026
Facilities staff recommended a $465,000 change order to add Trane open-protocol BAS controls to the Parkview project (raising the Parkview total to roughly $16.01 million), recommended multiple roofing contracts (~$1.6 million total), a marquee sign for Liberty ($36,773 with a $10,000 PTO donation) and an intercom/clock replacement ($959,415) to be funded from capital funds.
The full story
Facilities and operations staff presented multiple recommended procurements and a construction change order tied to ongoing capital projects.