Morris County utility officials report water-project progress, PFAS design work

Morris County Board of County Commissioners · May 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

An agency official updated commissioners on water and solid-waste operations, noting completion of Phase 1 of a 24-inch PCCP retirement, Phase 2 notice-to-proceed issued April 28 with a target completion date of August 26, a tank-cleaning contract awarded (low bid $58,570), and PFAS-treatment design advancing with NJDEP comments addressed.

An agency official (speaker 12) told the Morris County Board of County Commissioners that key water and utility capital projects are progressing and that solid-waste tonnage is up with spring season demand.

In a departmental update the official summarized operations and capital work: water sales trends were noted (transcript figures are partially garbled), Phase 1 of a 24-inch PCCP retirement reached final completion, and Phase 2 received a notice to proceed on April 28 with a completion target of August 26. The official also said a tank-cleaning contract was awarded to Cicaturo Brothers and Alpine Painting and Sandblasting as low bidders and referenced the low-bid figure of $58,570.

The official reported PFAS-treatment design work at Flanders Valley (number 1 and number 2) is advancing and that NJDEP comments have been addressed for the designs. The update also referenced generator and electrical improvement work at Alimatang Wells numbers 4 and 5 and noted continuing work with New Jersey American Water on a new public-service project in Mount Olive.

Regarding solid-waste operations the official said transfer-station tonnage remains stable and is increasing with the spring season; the county awarded a collection and disposal contract to Waste Management of New Jersey and is undertaking scale-replacement projects.

The board did not vote on new capital allocations during the presentation. Several commissioners thanked staff for the progress report and asked that staff continue routine procurement and compliance checks; one commissioner later asked that a consent-agenda resolution be pulled over a separate contractor-registration concern (see separate article).