Black Hawk County accepted final completion for several bridge repairs (Project L3032) and placed seal-coating bids for FY27 on file; the bridge contract final cost was presented as roughly $314,992 and bids ranged from $164,196 to $284,300.

The full story

County Engineer Kathy Nicholas briefed the board May 26 and recommended final acceptance of Project L3032 (bridge repairs performed by Boulder Construction LLC). Staff described deck and drip-edge repairs on several county bridges, change orders including a $75,000 Donald Street addition, and a final project cost presented in the meeting materials at about $314,991.90. The board approved final acceptance, release of retainage and closeout.