Cle Elum transfer-station entrance work underway; contractor to remove trees before 45-day completion
Summary
County staff said the Cle Elum Transfer Station entrance project has begun; contractor crews are surveying and laying out tree removals and staff expect the project to be finished about 45 days after those initial steps.
Patti Stacey, a county staff member, updated the commissioners that the Cle Elum Transfer Station entrance project has begun. She said the contractor would survey the site and lay out locations for tree removal as the next step, and staff expect the project to be completed in about 45 days following those activities.
The report was given as a project-status update; no board action or funding decisions were recorded at the May 12 meeting.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.